Capital Programme 2017/18

Decision Maker: Co-operative Executive

Decision status: Recommmend Forward to Council

Is Key decision?: Yes

Purpose:

The report sets out the proposed Capital Programme for 2017/18 onwards, describing the programmes to be undertaken, lists the projects to be delivered and sets out the context it which it has been compiled.

Decision:

12.1

The Acting Executive Director, Resources submitted a report setting out the proposed Capital Programme from 2017-18 onwards describing the programmes to be undertaken, listing the projects to be delivered and setting out the context in which it has been compiled. 

 

 

12.2

RESOLVED: That Cabinet recommends to the meeting of the City Council on 3rd March 2017:-

 

 

 

(a)

that Members note the specific projects included in the years 2017-18 to 2022-23 programmes at Appendix 9. Block allocations are

included within the programme for noting at this stage and detailed proposals will be brought back for separate Member approval as part of the monthly monitoring procedures;

 

 

 

 

(b)

to Note the proposed Capital Programme for the 6 years to 2022/23 as per Appendix 9 of the report; and

 

 

 

 

(c)

Approve the Corporate Resource Pool policy outlined in Appendix 4 such that the commitment from the CRP is limited to one year and no CRP supported schemes are approved beyond 2017/18 unless explicitly stated. Further reports will be brought to Members as part of the monthly approval process should the receipts position improve.

 

 

 

12.3

Reasons for Decision

 

 

12.3.1

The proposed projects within the Capital programme will improve the services  to the people of Sheffield

 

 

12.3.2

To formally record the Capital Programme in line with the Council’s annual budgetary procedures and gain Member approval for the policy on the management of the Corporate Resource Pool.

 

 

12.4

Alternatives Considered and Rejected

 

 

12.4.1

A number of alternative courses of action are considered as part of the capital approval process undertaken by Officers before decisions are recommended to Members. The recommendations made to Members represent what Officers believe to be the best options available to the Council, in line with Council priorities, given the constraints on funding and the use to which funding is put within the Revenue Budget and the Capital Programme.

 

 

12.5

Any Interest Declared or Dispensation Granted

 

 

 

None

 

 

12.6

Reason for Exemption if Public/Press Excluded During Consideration

 

 

 

None

 

 

12.7

Respective Director Responsible for Implementation

 

 

 

Acting Executive Director, Resources

 

 

12.8

Relevant Scrutiny and Policy Development Committee If Decision Called In

 

 

 

N/A

 

 

 

(Note: This is subject to approval at Full Council at its meeting to be held on 3 March 2017 and is not subject to call-in).

 