Decision details

Demolition Of Former Tinsley Junior School

Decision Maker: Assistant Commercial Director

Decision status: Recommendations Approved

Decision:

(i) Proceed to award the Term Contract to Hague Plant Limited for £115,780.00; and

 

(ii) a Letter of Acceptance issued accordingly.

 

Reasons for the decision:

To award a Contract to enable the works to commence from July 17.

 

The contract award report provides further details on the evaluation scores, tender prices and ranking of bidders.

Alternative options considered:

To reject the outcome of the process would mean a delay to this project and works would not go ahead.

Publication date: 18/07/2017

Date of decision: 22/05/2017

Accompanying Documents: