Decision details
Asbestos Surveyor and Project Management Framework 2016 -19
Decision Maker: Assistant Commercial Director
Decision status: Recommendations Approved
Decision:
(i) Proceed to award the Term Contract to Qualsurv International Ltd; and
(ii) a Letter of Acceptance will be issued accordingly.
Reasons for the decision:
To award a Contract to enable the works to commence from December 2016
The contract award report provides further details on the evaluation scores, tender prices and ranking of bidders.
Alternative options considered:
To reject the outcome of the process would mean a delay to this project and the framework not being established.
Publication date: 19/05/2017
Date of decision: 10/01/2017
Accompanying Documents: