Decision details
Demolition Of Former Tinsley Junior School
Decision Maker: Assistant Commercial Director
Decision status: Recommendations Approved
Decision:
(i) Proceed to award the Term Contract to Hague Plant Limited for £115,780.00; and
(ii) a Letter of Acceptance issued accordingly.
Reasons for the decision:
To award a Contract to enable the works to commence from July 17.
The contract award report provides further details on the evaluation scores, tender prices and ranking of bidders.
Alternative options considered:
To reject the outcome of the process would mean a delay to this project and works would not go ahead.
Publication date: 18/07/2017
Date of decision: 22/05/2017
Accompanying Documents: