7.1
|
The Committee received a report of the Interim
Director of Council Housing which provided Members with details of
the new contract for Repairs and Maintenance Services to
tenants’ homes, which had been agreed between the Council and
Kier Services and which would start on 1st April 2014,
and run for 3 years (with the option to extend by up to 2 more
years). The report was presented by
Janet Sharpe, Interim Director of Council Housing, who referred to
the procurement process, the consultation involved and the aims of
the contract.
|
|
|
7.2
|
Members
made various comments and asked a number of questions, to which
responses were provided as follows:-
|
|
|
|
·
It was important to ensure value for money but not compromise on
quality. A target of 5% efficiency
savings had been set but this would not be achieved at the expense
of the quality of the service.
|
|
|
|
·
There would only be marginal savings with the 5 years plus 2 years
option, so 3 years plus 2 years had been agreed as the duration of
the contract.
|
|
|
|
·
There were 6/700 Council officers working within the contract and
the day to day workers would transfer to Kier under the Transfer of
Undertakings (Protection of Employment) Regulations
(TUPE). All the submitting contractors
were large national organisations who had previously worked in
Sheffield, but Kier had management in place which would create
stability for the workforce.
|
|
|
|
·
Issues such as multiple visits for repairs, the empowering of
operatives and dealing with more difficult repairs were intended to
be addressed in the contract. This
would be achieved by creating a multi-tasking workforce with the
appropriate skills and tools, improved analysis, and the monitoring
of salary and bonus arrangements using key performance
indicators. It was intended to move to
a salary system only over the next 3 years to support a cultural
change from a system where the bonus scheme reflected the number of
visits to a property. The aim was to
have a more modernised workforce to the benefit of customers.
|
|
|
|
·
The intention was to ensure that planned work was done whilst
achieving the best value for money. The
number of visits to complete a repair was proving to be a barrier,
so the approval process was being looked at to see how far
operatives could make their own decisions. Technology was being used to achieve this, but it
was appreciated that this change would take time, as systems which
had been in place for ten years would have to be
changed. Operatives would need to be
confident as to their decisions and their managers would need to
know that budgets were not being exceeded.
|
|
|
|
·
The workforce should be trained to identify situations where
asbestos was an issue, so that the Council’s database of such
locations could be updated. Under the
new contract, Kier would procure responsive skills to deal with
asbestos in a more flexible manner.
|
|
|
|
·
In relation to adaptations, it was felt that a more holistic
approach was required with regard to both public and private
works.
|
|
|
7.3
|
RESOLVED: That the Committee:-
|
|
|
|
(a) thanks Janet Sharpe
for her contribution to the meeting; and
|
|
|
|
(b) notes the contents of the report and the responses
to questions.
|