This report seeks approval to utilise the clause within a current contract for dispersed supported housing service for young people for a period of up to one year from 2nd February 2018 to 1st February 2019.
The current contract provides support accommodation in a range of properties dispersed across the City. The current contract price is £485,000.
The current contract was let in 2015 for three years plus the ability to extend for a further two years, one year at a time.
The Council wishes to extend the contract for up to a year until 1st February 2019. A wider review of all our young people’s housing related support contracts is underway and a new commissioning plan will be completed by the end of spring 2018. The Commissioning Plan will seek to recommission all supported accommodation for young people
Extending this contract for up to a year will allow this service to continue whilst the commissioning plan is approved and all new supported accommodation services for young people are procured and service models implemented.
The current contract has provision for:
The Council has identified ways in which the provision can be used in a more cost effective way, which involves:
· increasing supported accommodation for young parents
· reducing the overall number of properties by taking out those of low quality or in areas of high concentration of supported housing and swopping some units of accommodation to widen location of supported housing
· reducing the resettlement role to retain funding of support in supported accommodation.
· reducing the contract fee by £30,000.
The future contract will have provision for:
Decision Maker: Director of Commissioning, Inclusion and Learning
Decision published: 31/01/2018
Effective from: 31/01/2018
Decision:
That the contract held by Depaul UK, be extended for one up to one year (from 2nd February 2018 to 1st February 2019) at a reduced contract price of £455,000 (a £30,000 reduction) and a reduction of 7 supported accommodation units.
Lead officer: Dawn Walton
Sheffield City Council has been awarded £500,000 by Visit England as part of Visit England’s Discover England Fund. The funding will enable the Council to create adrenaline fuelled city breaks designed to attract international adventure sports enthusiasts.
This report seeks the approval for the Council to act as Accountable Body and to accept a grant offer from Visit England for the above project.
Decision Maker: Executive Director, Place
Decision published: 29/01/2018
Effective from: 26/01/2018
Decision:
That the Executive Director, Place:-
(i) agrees that Sheffield City Council will act as Accountable Body for the Adrenaline Fuelled City Break Project; and
(ii) authorises the Council to accept the grant offer from Visit England for £500,000 and notes the requirement that this will need to be spent by March 2019.
Lead officer: Jen Rickard
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of North Midland Construction PLC in the sum of £749,028.68 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of ANSA Elevators Ltd in the sum of £1,737,423.00 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of Wates Construction Ltd in the sum of £10,303,306.91 be accepted;
(ii) the tender of Kier Services Ltd in the sum of £10,699,166.40 be accepted; and
(iii) letters of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of Construction Marine Ltd in the sum of £160,030.00 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of Doe Sport in the sum of £108,173.40 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 29/01/2018
Effective from: 14/12/2017
Decision:
(i) The tender of Beashem Asphalt Ltd in the sum of £185,668.00 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of Amey Hallam Highways in the sum of £93,161.2 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of O&P Construction Services Ltd in the sum of £228,343.53 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of Sheffield City Council’s Playground Team in the sum of £81,122.50 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of Amey Hallam Highways in the sum of £189,595 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of EC Surfacing Ltd in the sum of £116,903.51 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 20/07/2016
Decision:
(i) The tender of T H Michaels (Construction) Ltd in the sum of £49,792.00 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of Amey Hallam Highways in the sum of £61,560.50 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Director of Commercial Services
Decision published: 26/01/2018
Effective from: 07/07/2017
Decision:
(i) The tender of Turner and Townsend be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
Decision Maker: Assistant Commercial Director
Decision published: 26/01/2018
Effective from: 07/12/2017
Decision:
(i) The tender of Kier Construction (Northern) Ltd in the sum of £23,420,710 be accepted; and
(ii) a Letter of Acceptance issued accordingly.
Lead officer: Tim Hardie
To advise the Leader of progress on the disposal of land at Upper Hanover Street since a decision was made by Cabinet in October 2006 and to seek rescission of that decision in order to progress the sale.
Decision Maker: Leader of the Council
Decision published: 23/01/2018
Effective from: 30/01/2018
Decision:
That the Leader:-
(a) agrees to rescind the Cabinet decision of 11 October 2006 that “authority be given to progress Phase 1 as a disposal at market value, under the authority delegated to the Head of Corporate Property and the City Property Manager, with the development having regard to the Masterplan vision, and the receipt earmarked for filling-in the underpass beneath Hanover Way as now reported”;
(b) authorises the disposal of the land initially to BM Development Services Limited, and secondly to Mr Merricks if BM Development Services fail to exchange by 31st January or complete by conditional dates set out in the contract; and
(c) if neither party has exchanged contracts by the end of January or alternatively if contracts have been exchanged but the disposal has not completed by the conditional date contained in the contract, authorises the Chief Property Officer to dispose of the site on the open market.