Decision details

Procurement of Gas Supply

Decision Maker: Executive Director, Place

Decision status: Recommendations Approved

Is Key decision?: Yes

Purpose:

SCC’s gas requirements have been met by calling off from the Yorkshire Purchasing Organisation (YPO) gas framework agreement.  The framework was competitively procured by YPO in line with the (2006) Public Procurement Regulations, and was OJEU compliant.  British Gas (BG) were the successful tenderer and accordingly the Council entered into a contract with British Gas (BG) on 1 June 2013 for a fixed term of 46 months through to 31 March 2017 (leaving just over a year left to run).

 

The report is about successor arrangements for when the current YPO framework / BG contract expires.

Decision:

The Executive Director:-

 

approves the Council remaining with its current supplier, British Gas, until 31st March 2017 when the existing contract expires; and

 

approves the Council continuing its membership with Yorkshire Procurement Organisation for the next framework period – a maximum of four years (till 31st March 2021).

Reasons for the decision:

The recommendation from the report is to allow the existing contract with British Gas to expire on the 31st March 2017 and subsequently enter into a supply agreement with Corona Energy.

 

This is considered to be the best option due to the timescale it would require to establish new supplier. It will also provide circa £75k annual savings on energy spent as the new contract offers lower contract management fee.

Alternative options considered:

A list of alternative options has been provided within CLOSED Appendix 1: Option Appraisal – Gas Supply. An overview of this paper has been set out as below:

 

Decommissioning of gas supply. This option is not achievable as the Council requires a gas supply to deliver heat and hot water services to its own premises and to premises of associated members i.e. schools, housing, etc.

 

Serve notice of early termination on the current gas supply contract with YPO/British Gas. Termination would realistically require a minimum of six months to complete, and with less than a year left of the framework the earliest the Council could end the agreement would be March 2017.   If termination did go ahead, an alternative supplier would also need to procured, which requires full procurement process and would not be completed on time for end of the year. There would be a cost for early termination and potentially the Council could be exposed to the challenge from British Gas and YPO.

 

The Council buys its own energy or runs its own procurement exercise. The Council setting up its own energy buying unit is an area for further consideration in the long term, as there is not sufficient time to prepare this strategy within the 7 month time limit. Buying in-house is an approach followed by Liverpool City Council for example.  A detailed consideration of this is beyond the scope of this report and proposal would require a full Business Case developing and taking through the Council’s normal approval route with Commercial Services involvement.

 

 

Publication date: 12/09/2016

Date of decision: 12/09/2016

Effective from: 17/09/2016

Accompanying Documents: