Decision details
Gleadless SEN Pupil Places: Stage 1 Design & Build
Decision Maker: Head of Commercial Business Development
Decision status: Recommendations Approved
Is Key decision?: Yes
Purpose:
Contract award to Module-AR Limited (M-AR) by negotiation via the LHC Framework.
Decision:
That (1) the tender of Module-AR Limited (M-AR) in the sum of £502,000 to undertake Stage 1 work is accepted; and
(2) a Letter of Acceptance is issued accordingly.
Decision taken by the Director of Finance & Commercial Services or her nominee under the authority delegated by Cabinet on 17.02.2021.
For further information regarding the decision, please see Agenda Item 10, Appendix 1
https://democracy.sheffield.gov.uk/ieListDocuments.aspx?CId=123&MId=7553&Ver=4
for further information regarding the project, please contact patricia.slater@sheffield.gov.uk
Reasons for the decision:
To award a contract to enable works to commence May 2021.
Alternative options considered:
None.
The above contracts have been awarded in accordance with approved tender processes and the budgets are in place.
Publication date: 28/07/2021
Date of decision: 27/05/2021