8.1

The Senior Capital and Construction Category Manager introduced the report which provided details of proposed changes to the existing Capital Programme as brought forward in Month 03 2024/25.

 

8.2

RESOLVED UNANIMOUSLY: That the Finance and Performance Policy Committee:-

  1. That the committee approve the proposed additions and variations to the Capital Programme listed in Appendix 1.
  2. That the committee approve the proposed variation to the Capital Programme identified in Appendix 2 subject to a successful outcome of the external funding bid.
  3. That the committee approve the acceptance of grant funding as identified in Appendix 2

 

8.3

Reasons for Decision

8.3.1

The proposed changes to the Capital programme will improve the services to the people of Sheffield.

8.3.2

To formally record changes to the Capital Programme and gain Member approval for changes in line with Financial Regulations and to reset the capital programme in line with latest information.

 

8.4

Alternatives Considered and Rejected

8.4.1

A number of alternative courses of action are considered as part of the process undertaken by Officers before decisions are recommended to Members. The recommendations made to Members represent what Officers believe to be the best options available to the Council, in line with Council priorities, given the constraints on funding and the use to which funding is put within the Revenue Budget and the Capital Programme.

 