Decision Maker: Leader of the Council
Decision status: Recommendations Approved
Is Key decision?: Yes
A review of the commissioning and delivery arrangements for young people’s services is underway. In order to allow time to conclude the Leader Review of Young People’s Services and the subsequent implementation of the outcomes of the review and any new delivery model this report requests approval for the extension and/or re-procurement of a number of Young People’s support services while this review is concluded to ensure continuity of support and provide a legal framework for continued delivery of existing provision up to 30 September 2020.
In order to allow time to conclude the Leader Review of Young People’s Services and the subsequent implementation of the outcomes of the review and any new delivery model, the Leader is recommended to approve the following actions which will provide a legal framework for continued delivery of existing provision until 30 September 2020 should this be required:
Take any other action necessary, including extending or breaking contracts in accordance with their terms, as may be required to facilitate the outcomes outlined in this Report.
Extending/re-procuring current provision to the end of September 2020 will ensure uninterrupted service for young people and enables the Council to continue to fulfil a number of statutory duties and will allow time to make a strategic decision about the future delivery of young people services. Insufficient time to commission robustly has necessitated a moving back of timelines so that full consideration of options can be made through the review process and robust procedures implemented for commissioning for new or reshaped services.. |
|
If we do not proceed as proposed current services to vulnerable young people may cease to operate and the Council is unlikely to be able to deliver all of these services directly. |
|
Extending/re-procuring these services allows the Council to continue to meet a number of statutory duties. |
An alternative option considered was to extend/re-procure all the contracts so that they had an end date of 30th September 2019. This option has been rejected because, at best, this gives only 11 months to conduct a potentially complex service redesign, commissioning and implementation process. If the process is not completed by that date extensions or re-procurements would then be required at potentially short notice and extra cost. |
|
An alternative option considered was to allow some, or all, of the contracts to expire, and transfer the service delivery from the current provider to the Council. This option has been rejected because the services are complex (for example including use of buildings the Council does not own), and include a significant range of resources and staff. It is estimated that this option would take many months to implement, and is not a viable short term solution. |
Urgent item?: Yes
Publication date: 28/09/2018
Date of decision: 26/09/2018
Accompanying Documents: