Agenda item

Housing Capital Programme - 2023/24 Quarter 4 update on the approved 5 Year Programme

Report of the Executive Director Neighbourhood Services

Decision:

7.1

Members considered a report of the Executive Director, Neighbourhood Services providing a quarterly update on progress against the approved 2023/24 Housing Capital Programme. The report focussed on providing an update on expenditure and progress against the 2023/24 Housing Capital Programme position at the end of March 2024 (Quarter 4). The report also provided an update of the 5-year Housing Capital Programme (2023/24 – 2027/28).

 

 

7.2

RESOLVED UNANIMOUSLY: That the Housing Policy Committee:-

 

       Notes the 2023-24 Housing Capital Programme outturn and budget position at the end of quarter 4.

       Notes the update provided for the 5-year Housing Capital Programme (2023/24 – 2027/28)

 

 

 

 

7.3

Reasons for Decision

7.3.1

This report is to provide the Housing Policy Committee members with an update on

progress against the 5-year approved Capital programme at the end of Qtr. 4

2023/24.

 

 

 

 

7.4

Alternatives Considered and Rejected

7.4.1

No alternative options are considered as part of this update report.

 

 

 

Minutes:

 

9.1.1

Members considered a report of the Executive Director, Neighbourhood Services providing a quarterly update on progress against the approved 2023/24 Housing Capital Programme. The report focussed on providing an update on expenditure and progress against the 2023/24 Housing Capital Programme position at the end of March 2024 (Quarter 4). The report also provided an update of the 5-year Housing Capital Programme (2023/24 – 2027/28).

 

 

9.1.2

A question was asked regarding the commencement of building at the Newstead General Housing Scheme in the Birley Ward and officers agreed to find this information and provide it to members after the meeting. An officer also confirmed the start date of the external refurbishment works on Edward Street as March 2025.

 

 

9.1.3

Officers were asked to provide start dates and indicative costs for all the projects listed in paragraph 2.5 of the report and it was agreed that these would be provided in writing after the meeting.

 

 

9.1.4

The Chair requested that the table in paragraph 2.4 be adjusted to separate out the carbon reduction elements from the heating and energy one, as was done for the HRA business plan, and for these to be recirculated to all members.

 

 

9.1.5

A query was raised regarding the start date for building work on the Older Persons Independent Living (OPIL) scheme in Gleadless Valley and also changes to the budget for the Gleadless Valley Masterplan. Officers agreed to look into this and provide an answer after the meeting.

 

 

9.2

RESOLVED UNANIMOUSLY: That the Housing Policy Committee:-

 

       Notes the 2023-24 Housing Capital Programme outturn and budget position at the end of quarter 4.

       Notes the update provided for the 5-year Housing Capital Programme (2023/24 – 2027/28)

 

 

9.3

Reasons for Decision

9.3.1

This report is to provide the Housing Policy Committee members with an update on

progress against the 5-year approved Capital programme at the end of Qtr. 4

2023/24.

 

 

 

 

9.4

Alternatives Considered and Rejected

9.4.1

No alternative options are considered as part of this update report.

 

 

 

Supporting documents: