Agenda item

South East Large Highways Schemes

Report of the South East Community Assembly Manager

Decision:

1.1

The South East Community Assembly Manager submitted a report which outlined the current position with the allocation of Large Highways Schemes funds for the South East Community Assembly. 

 

 

1.2

RESOLVED: That the South East Community Assembly:-

 

 

 

(a)

requests that further assessment be given to the potential for the installation of:-

 

 

 

 

 

(i)      a one way system at Skelton Lane, Woodhouse; and

 

(ii)     crossing improvements at the junction of Springwater Avenue and Birley Spa Lane, Hackenthorpe

 

 

 

 

(b)

delegates the decision on which work to progress to the Community Assembly Manager, in conjunction with the Community Assembly Chair and Highways Link Officer, following the provision of further information on both schemes to all South East Community Assembly Members.

 

 

 

1.3

Reasons for Decision

 

 

 

The Community Assembly’s Highways budget needs to be allocated in the 2012-13 financial year.  It is currently assessing the possibilities and merits of two schemes and thus needs to delegate the final decision in order to meet funding deadlines.

 

 

1.4

Alternatives Considered and Rejected

 

 

 

The report outlined two different possible areas for work, one at Woodhouse (SkeltonLane/Spa Lane), where there were two different options under consideration, a one way system and waiting restrictions, and one at Hackenthorpe (Springwater Avenue/Birley Spa Lane).    Members were not pursuing information on any other large highways schemes at this time.

 

 

1.5

Any Interest Declared or Dispensation Granted

 

 

 

None declared.

 

 

1.6

Reason for Exemption if Public/Press Excluded During Consideration

 

 

 

Not applicable.

 

 

1.7

Respective Director Responsible for Implementation

 

 

 

Simon Green, Executive Director, Place Portfolio

 

 

1.8

Relevant Scrutiny and Policy Development Committee If Decision Called In

 

 

 

The relevant Scrutiny and Policy Development Committee to consider a call-in of the decision would be, in this instance, the Economic and Environmental Wellbeing Scrutiny and Policy Development Committee.

 

 

Minutes:

7.1

The South East Community Assembly Manager submitted a report which outlined the current position with the allocation of Large Highways Schemes funds for the South East Community Assembly. 

 

 

7.2

Decision Taken

 

 

 

RESOLVED: That the South East Community Assembly:-

 

 

 

(a)

requests that further assessment be given to the potential for the installation of:-

 

 

 

 

 

(i)      a one way system at Skelton Lane, Woodhouse; and

 

(ii)     crossing improvements at the junction of Springwater Avenue and Birley Spa Lane, Hackenthorpe; and

 

 

 

 

(b)

delegates the decision on which work to progress to the Community Assembly Manager, in conjunction with the Community Assembly Chair and Highways Link Officer, following the provision of further information on both schemes to all South East Community Assembly Members.

 

 

 

7.3

Reasons for Decision

 

 

 

The Community Assembly’s Highways budget needs to be allocated in the 2012-13 financial year.  It is currently assessing the possibilities and merits of two schemes and thus needs to delegate the final decision in order to meet funding deadlines.

 

 

7.4

Alternatives Considered and Rejected

 

 

 

The report outlined two different possible areas for work, one at Woodhouse (SkeltonLane/Spa Lane), where there were two different options under consideration, a one way system and waiting restrictions, and one at Hackenthorpe (Springwater Avenue/Birley Spa Lane).    Members were not pursuing information on any other large highways schemes at this time.

 

Supporting documents: