25/02/2021 - Porter Brook Site / Broadfield Road Site Demolition ref: 2757    Recommendations Approved

Contract award to Demolition, Contracting & Environmental Services (DCE) Ltd

Decision Maker: Head of Commercial Business Development

Decision published: 30/03/2021

Effective from: 25/02/2021

Decision:

That the tender of Demolition, Contracting & Environmental Services (DCE) Ltd in the sum of £226,566.65is accepted; and

 

A Letter of Acceptance is issued accordingly.

 

Decision taken by the Director of Finance & Commercial Services or her nominee under the authority delegated by Cabinet on 18.11.2020.

 

For further information regarding the decision, please see Agenda Item 9, Appendix 1 below:

 

https://democracy.sheffield.gov.uk/ieListDocuments.aspx?CId=123&MId=7550&Ver=4

 

For further information regarding the project, please contact Tammy Whittaker or Tom Finnegan-Smith.

Lead officer: Tim Hardie


25/02/2021 - Hillsborough All Wheels Bike Park ref: 2756    Recommendations Approved

Contract award to Architrail Velosolutions UK Ltd

Decision Maker: Head of Commercial Business Development

Decision published: 30/03/2021

Effective from: 25/02/2021

Decision:

That the tender of Architrail Velosolutions UK Ltd in the sum of £253,730.34 is accepted; and

 

A Letter of Acceptance is issued accordingly.

 

Decision taken by the Director of Finance & Commercial Services or her nominee under the authority delegated by Cabinet on 17.06.2020.

 

For further information regarding the decision, please see Agenda Item 12, Appendix 1 below:

 

https://democracy.sheffield.gov.uk/ieListDocuments.aspx?CId=123&MId=7546&Ver=4

 

For further information regarding the project, please contact Lisa Firth.

Lead officer: Tim Hardie


25/02/2021 - Portobello cycle route crossings (Mappin Street) ref: 2755    Recommendations Approved

Contract award to Amey Hallam Highways

Decision Maker: Head of Commercial Business Development

Decision published: 30/03/2021

Effective from: 25/02/2021

Decision:

That the tender of Amey Hallam Highways in the sum of £519,840.64 is accepted; and

 

A Letter of Acceptance is issued accordingly.

 

Decision taken by the Director of Finance & Commercial Services or her nominee under the authority delegated by Cabinet on 17.07.2019.

 

For further information on the decision, please see Agenda Item 11, Appendix 1 below:

 

https://democracy.sheffield.gov.uk/ieListDocuments.aspx?CId=123&MId=7259&Ver=4

 

for further information regarding the project, please contact Tom Finnegan-Smith.

Lead officer: Tim Hardie


25/02/2021 - Electric Van Centre of Excellence Project ref: 2754    Recommendations Approved

Contract awards to:

 

Bristol Street Motors

Franklin Energy

Big Change  

YESSS Electrical

Richmond Electrical.

Decision Maker: Head of Commercial Business Development

Decision published: 30/03/2021

Effective from: 25/02/2021

Decision:

That the combined tenders in the sum of £870.050.40 is accepted; and

 

Letters of Acceptance are issued accordingly.

 

Decision taken by the Director of Finance & Commercial Services or her nominee under the authority delegated by Cabinet on 15.07.2020.

 

For further information regarding the decision, please see Agenda Item 8, Appendix 1 below:

 

https://democracy.sheffield.gov.uk/ieListDocuments.aspx?CId=123&MId=7547&Ver=4

 

For further information regarding the project, please contact Tom Finnegan-Smith

Lead officer: Tim Hardie


26/02/2021 - Upper Don flood alleviation scheme - Agreement with the Environment Agency ref: 2730    Recommendations Approved

This report seeks authority for the Council to conclude an agreement (‘the Agreement’) with the Environment Agency (‘EA’) which will give the Council the necessary statutory authority to progress the Upper Don flood alleviation scheme (‘the Scheme’).

 

As the Upper Don is categorised as a ‘Main River’ the statutory powers to carry out works on this river in relation to flood risk management lie with the EA, not the Council.  However, the EA has given approval for the Council to implement a flood alleviation scheme on the Upper Don.  Indeed, it is contributing funding for the Scheme.  As it is the Council who are implementing the Scheme, they require the same statutory powers (in relation to the Scheme) as the EA. Accordingly the EA has agreed to enter into the Agreement to confer certain necessary statutory authorisations on the Council and to make certain other arrangements relating to the Scheme.

 

Decision Maker: Executive Director, Place

Decision published: 12/03/2021

Effective from: 26/02/2021

Decision:

RESOLVED that:

 

the City Council enter into an agreement with the Environment Agency in the form appended to the report.

 

Lead officer: Dave Brown


10/03/2021 - Treevitalise Project : Woodland Trust's Emergency Tree Fund Grant ref: 2719    Recommendations Approved

To seek approval to accept the £183,319 of funding from the Woodland Trust’s Emergency Tree Fund following Sheffield City Council’s Community Forestry Team’s successful bid, and to deliver the Treevitalise Project.

Decision Maker: Executive Director, Place

Decision published: 11/03/2021

Effective from: 18/03/2021

Decision:

That the Executive Director:-

 

(a) approves the Council accepting the funding of £183,319 from the Woodland Trust’s Emergency Tree Fund;

 

(b) approves the Treevitalise Sheffield project being delivered as outlined in the report; and

 

(c) approves the Council entering into a Grant Agreement with the Woodland Trust.

 

 

Lead officer: Dave Aspinall


09/03/2021 - Acceptance of government grant for Asymptomatic Test Site(s) ref: 2710    Recommendations Approved

Decision Maker: Leader of the Council

Decision published: 10/03/2021

Effective from: 09/03/2021

Decision:

 

To:

 

1.    Approve delivery of the Asymptomatic Test Sites as outlined in the report.

 

2.    Approve acceptance of the Government grant associated with SCC delivery of asymptomatic testing.

 

Lead officer: Susan Hird


02/03/2021 - Acceptance of Sheffield City Region Funding for Reopening and Operating Ponds Forge Sports Centre ref: 2715    Recommendations Approved

To grant authority to accept external funding into the Council from Sheffield City Region for the purpose of meeting the costs to reopen Ponds Forge Sports Centre.

Decision Maker: Leader of the Council

Decision published: 05/03/2021

Effective from: 02/03/2021

Decision:

That the Leader of the Council:-

 

1.    approves Sheffield City Council becoming the Accountable Body for third party liabilities and payments of the grant to Sheffield City Trust up to a value of £2.388m on the basis outlined in the report;

 

  1. notes that arrangements will be put in place to finalise the funding arrangements and put in place any required monitoring/reporting arrangements; and

 

  1. delegates authority to the Director of Culture and Environment, in consultation with the Director of Legal and Governance and the Director of Finance and Commercial Services, to take such steps not already delegated as they deem appropriate to achieve the outcomes set out in the report.

 

Lead officer: Tammy Barrass


26/02/2021 - SEND Mediation and Disagreement Resolution Service ref: 2709    Recommendations Approved

The current contract for the SEND Mediation and Disagreement Resolution service is due to expire on 31st March 2021. In order to prevent a gap in service and meet the Local Authority’s statutory duty to provide the provision, we seek approval for the following:

         To conduct a Request for Quote/tender exercise through the Sourcing Desk (Procurement) to find a servicer provider

         Award a 2 year Sheffield City Council contract, with a 1 year break clause to the successful bidder

Decision Maker: Director of Education and Skills

Decision published: 26/02/2021

Effective from: 26/02/2021

Decision:

Agreed:

 

1.       approval be given to the proposed services as set out in this report and to procure such services in line with this report; and

 

2.       approval be given to the contract award following such procurement exercise, in consultation with the Director of Finance and Commercial Services and thereafter to take such other necessary steps not covered by existing delegations to achieve the outcomes and objectives of this report.

Lead officer: Lucy Hagan